Pima County has made indications of re-starting the building construction process. Obviously, an agreed upon Intergovernmental Agreement will have to be processed prior to a re-start. Pima County will manage the project in its entirety. The Library department will acquire and process the book collection and will acquire and install all the technology components for the Library and Learning Center. Pima County will provide funds to accomplish these two major tasks.
Were Pima County to authorize a re-start date in January 1, 2002, a building time line would look something like the following:
October to December 2002 Once Schematic design phase is completed, the Architect moves onward to the Design Development phase. This is the last phase of architectural work. All the fine details of the building as a whole are developed.
January to March 2003 Construction Documents are developed which are put out for bid and a Contractor is hired to build the facility.
April to September 2003 the building is under Construction, furnishing and equipment are ordered and the book collection (development started a year ago) is about to be delivered.
October to December 2003 - Move in.